UPGRADE GUARDRAIL AND END
FROM 0.3 MILE SOUTH OF NORTH FORK SAN GABRIEL RIVER OVERCROSSING TO 0.3 MILE NORTH OF NORTH CRYSTAL
| Bid opened | 2022-01-12 |
|---|---|
| District | 07 |
| Engineer's estimate | $5,700,000.00 |
| Low bid | $5,981,239.00 4.93% vs EE |
| Low bidder | BOSCO CONSTRUCTORS, INC. |
| Number of bidders | 4 |
| Working days | 250 |
| Number of items | 72 |
| Source | Caltrans bid summary PDF ↗ |
| # | Bidder | City, State | Bid amount | vs Low |
|---|---|---|---|---|
| 1 | BOSCO CONSTRUCTORS, INC. | CHATSWORTH, CA | $5,981,239.00 | +0.0% |
| 2 | BEADOR CONSTRUCTION COMPANY, INC. | CORONA, CA | $6,638,700.00 | +11.0% |
| 3 | FEC FUTURE CONTRACTORS AND ENGINEERS | IRVINE, CA | $6,998,244.18 | +17.0% |
| 4 | JILK HEAVY CONSTRUCTION, INC. | BREA, CA | $8,463,707.25 | +41.5% |