Construct soldier pile wall and structural concrete barrier slab.
MONTEREY COUNTY NEAR BIG SUR ABOUT 1.1 MILES SOUTH OF PFEIFFER CANYON BRIDGE
| Bid opened | 2025-11-18 |
|---|---|
| District | 05 |
| Engineer's estimate | $3,400,000.00 |
| Low bid | $3,034,376.10 -10.75% vs EE |
| Low bidder | GRANITE ROCK COMPANY |
| Number of bidders | 7 |
| Working days | 425 |
| Number of items | 76 |
| Source | Caltrans bid summary PDF ↗ |
| # | Bidder | City, State | Bid amount | vs Low |
|---|---|---|---|---|
| 1 | GRANITE ROCK COMPANY | SAN JOSE, CA | $3,034,376.10 | +0.0% |
| 2 | GORDON N. BALL, INC. | WALNUT CREEK, CA | $3,355,573.00 | +10.6% |
| 3 | TAYLOR JANE CONSTRUCTION LP NR DVBE GOAL NOT MET 427 SOUZA DR COMPARISON AMT: NIPOMO CA 93444 714,499.35 IN ACCORDANCE WITH G.C.14838, THE DEPARTMENT OF TRANSPORTATION SHALL APPLY THE SMALL BUSINESS PREFERENCE TO ELIGIBLE FIRMS FIRST, THEN APPLIES THE NON-SMALL BUSINESS PREFERENCE IF DOING SO WOULD NOT DISPLACE A SMALL BUSINESS FROM AWARD OF THE CONTRACT. 05-0Q5004 BID211 05-MON-1-20 PAGE 2 08/19/20 09/11/20 L I S T O F S U B C O N T R A C T O R S | NIPOMO, CA | $3,685,613.00 | +21.5% |
| 4 | VIKING CONSTRUCTION COMPANY, INC. | RANCHO CORDOVA, CA | $3,868,615.00 | +27.5% |
| 5 | MYERS & SONS CONSTRUCTION, LLC | SACRAMENTO, CA | $3,898,890.00 | +28.5% |
| 6 | JOHN MADONNA CONSTRUCTION CO., INC. | SAN LUIS OBISPO, CA | $4,160,091.50 | +37.1% |
| 7 | GRANITE CONSTRUCTION COMPANY | SANTA BARBARA, CA | $4,531,412.00 | +49.3% |