Cold plane AC pavement and rubberized HMA-O.
YUBA COUNTY AT AND NEAR OLIVEHURST FROM ROUTE 65/70 SEPARATION TO YUBA RIVER BRIDGE
| Bid opened | 2026-03-25 |
|---|---|
| District | 03 |
| Engineer's estimate | $3,890,000.00 |
| Low bid | $3,294,612.00 -15.31% vs EE |
| Low bidder | ALL-AMERICAN CONSTRUCTION, INC. |
| Number of bidders | 9 |
| Working days | 45 |
| Number of items | 50 |
| Source | Caltrans bid summary PDF ↗ |
| # | Bidder | City, State | Bid amount | vs Low |
|---|---|---|---|---|
| 1 | ALL-AMERICAN CONSTRUCTION, INC. | SUTTER, CA | $3,294,612.00 | +0.0% |
| 2 | DESILVA GATES CONSTRUCTION, LLC | DUBLIN, CA | $3,329,329.00 | +1.1% |
| 3 | LAMON CONSTRUCTION CO., INC. | YUBA CITY, CA | $3,394,814.50 | +3.0% |
| 4 | MOUNTAIN CASCADE, INC. | LIVERMORE, CA | $3,543,862.30 | +7.6% |
| 5 | MERCER-FRASER COMPANY | FORTUNA, CA | $3,631,631.00 | +10.2% |
| 6 | A. TEICHERT & SON, INC. DBA TEICHERT | SACRAMENTO, CA | $3,662,824.50 | +11.2% |
| 7 | BALDWIN CONTRACTING CO., INC. DBA KNIFE | CHICO, CA | $3,718,193.36 | +12.9% |
| 8 | GRANITE CONSTRUCTION COMPANY | SACRAMENTO, CA | $4,241,512.41 | +28.7% |
| 9 | GEORGE REED, INC. | MODESTO, CA | $4,380,063.00 | +32.9% |
CaltransTracker.com is an independent, privately owned data platform. It is not affiliated with, endorsed by, or operated by the California Department of Transportation (Caltrans) or the State of California. About · Privacy · Terms · Support this site