CULVERT REHABILITATION
IN SAN DIEGO COUNTY AT VARIOUS LOCATIONS FROM 0.7 MILE WEST OF FLINN SPRINGS ROAD UNDERCROSSING TO
| Bid opened | 2022-01-05 |
|---|---|
| District | 11 |
| Engineer's estimate | $7,000,000.00 |
| Low bid | $5,458,489.00 -22.02% vs EE |
| Low bidder | HAZARD CONSTRUCTION ENGR, LLC |
| Number of bidders | 7 |
| Working days | 480 |
| Number of items | 60 |
| Source | Caltrans bid summary PDF ↗ |
| # | Bidder | City, State | Bid amount | vs Low |
|---|---|---|---|---|
| 1 | HAZARD CONSTRUCTION ENGR, LLC | LAKESIDE, CA | $5,458,489.00 | +0.0% |
| 2 | GRIFFITH COMPANY | SANTA FE SPRINGS, CA | $5,481,481.00 | +0.4% |
| 3 | GRANITE CONSTRUCTION COMPANY | CARLSBAD, CA | $5,670,000.00 | +3.9% |
| 4 | LB CIVIL CONSTRUCTION, INC. | $5,742,624.00 | +5.2% | |
| 5 | BLUE PACIFIC ENGINEERING & CONSTRUCTION | SAN DIEGO, CA | $6,012,510.00 | +10.1% |
| 6 | BLOIS CONSTRUCTION, INC. NR LATE DBE/DVBE SUBMITTAL | OXNARD, CA | $6,067,795.90 | +11.2% |
| 7 | FEC FUTURE CONTRACTORS AND ENGINEERS | $6,796,728.90 | +24.5% |