CONSTRUCT RAISED CURB MEDIAN & LEFT
IN & NR MENIFEE & HEMET FROM 0.62 MI E/O RTE 215 TO 0.4 MI W/O ACACIA AVENUE
| Bid opened | 2019-02-21 |
|---|---|
| District | 08 |
| Engineer's estimate | $24,200,000.00 |
| Caltrans post-bid estimate | $24,515,308.57 (printed on the bid summary after bids opened) |
| Low bid | $19,711,791.00 -18.55% vs EE |
| Low bidder | GRANITE CONSTRUCTION COMPANY |
| Number of bidders | 4 |
| Working days | 465 |
| Number of items | 142 |
| Source | Caltrans bid summary PDF ↗ |
| # | Bidder | City, State | Bid amount | vs Low |
|---|---|---|---|---|
| 1 | GRANITE CONSTRUCTION COMPANY | INDIO, CA | $19,711,791.00 | +0.0% |
| 2 | SULLY-MILLER CONTRACTING COMPANY | BREA, CA | $21,483,000.00 | +9.0% |
| 3 | SEMA CONSTRUCTION, INC. | TEMECULA, CA | $22,798,624.02 | +15.7% |
| 4 | ALL AMERICAN ASPHALT | CORONA, CA | $25,274,326.00 | +28.2% |