RELINE OR REPLACE CULVERTS
AT VARIOUS LOCATIONS FR ZACA DR TO STA RTE 18 AT BIG BEAR LAKE DAM
| Bid opened | 2020-10-01 |
|---|---|
| District | 08 |
| Engineer's estimate | $2,540,000.00 |
| Caltrans post-bid estimate | $2,563,804.10 (printed on the bid summary after bids opened) |
| Low bid | $1,884,061.00 -25.82% vs EE |
| Low bidder | DREAMBUILDER CONSTRUCTION CORP DBA DREAMBUILDER |
| Number of bidders | 12 |
| Working days | 160 |
| Number of items | 52 |
| Source | Caltrans bid summary PDF ↗ |
| # | Bidder | City, State | Bid amount | vs Low |
|---|---|---|---|---|
| 1 | DREAMBUILDER CONSTRUCTION CORP. | YORBA LINDA, CA | $1,884,061.00 | +0.0% |
| 2 | BOSCO CONSTRUCTORS, INC. | CHATSWORTH, CA | $1,927,982.90 | +2.3% |
| 3 | RAL INVESTMENT CORPORATION DBA | SAN DIEGO, CA | $2,037,335.00 | +8.1% |
| 4 | IBARRA GENERAL ENGINEERING, INC. | RIVERSIDE, CA | $2,340,252.40 | +24.2% |
| 5 | O'DUFFY BROS INC. | ROMOLAND, CA | $2,473,606.50 | +31.3% |
| 6 | STRONGHOLD ENGINEERING OTHER REASON NOT AWARDED | PERRIS, CA | $2,535,129.00 | +34.6% |
| 7 | YAKAR | COVINA, CA | $2,535,150.30 | +34.6% |
| 8 | BEADOR CONSTRUCTION COMPANY, INC. | CORONA, CA | $2,729,700.00 | +44.9% |
| 9 | CENTRAL COAST FINANCIAL GROUP, INC. DBA | SONORA, CA | $2,778,000.00 | +47.4% |
| 10 | HIGHLAND CONSTRUCTION, INC. | ORANGE, CA | $2,788,792.50 | +48.0% |
| 11 | AUTOBAHN CONSTRUCTION, INC. | ORANGE, CA | $2,794,945.40 | +48.3% |
| 12 | LANDSCAPE SUPPORT SERVICES | NORTH HOLLYWOOD, CA | $2,869,626.53 | +52.3% |