Construct high-tension median cable barrier with vegetation control.
FRESNO COUNTY ABOUT 8 MILES WEST OF THREE ROCKS FROM PARKHURST EQUIPMENT UNDERCROSSING TO ROUTE 5/33 SEPARATION
| Bid opened | 2023-08-01 |
|---|---|
| District | 06 |
| Engineer's estimate | $1,630,000.00 |
| Low bid | $1,782,817.00 9.38% vs EE |
| Low bidder | CALIFORNIA HIGHWAY CONSTRUCTION GROUP, |
| Number of bidders | 4 |
| Working days | 30 |
| Number of items | 24 |
| Source | Caltrans bid summary PDF ↗ |
| # | Bidder | City, State | Bid amount | vs Low |
|---|---|---|---|---|
| 1 | CALIFORNIA HIGHWAY CONSTRUCTION GROUP | CONCORD, CA | $1,782,817.00 | +0.0% |
| 2 | CORAL CONSTRUCTION COMPANY | SHERWOOD, OR | $1,897,777.00 | +6.4% |
| 3 | MIDSTATE BARRIER, INC. | STOCKTON, CA | $2,290,110.00 | +28.5% |
| 4 | HIGHWAY SPECIALTY COMPANY, INC. | REDDING, CA | $3,275,065.00 | +83.7% |