Bridge preventive maintenance

FRESNO AND KERN COUNTIES IN FIREBAUGH ON ROUTE 33 FROM POSO CANAL BRIDGE TO COLONY MAIN CANAL BRIDGE AND NEAR MCKITTRICK ON ROUTE 58 AT MAIN DRAIN CANAL BRIDGE

Bid opened2023-08-29
District06
Engineer's estimate$1,770,000.00
Low bid$1,737,460.00 -1.84% vs EE
Low bidderBUGLER CONSTRUCTION, INC.
Number of bidders4
Working days60
Number of items33
SourceCaltrans bid summary PDF ↗

Bidders (4)

#BidderCity, StateBid amountvs Low
1 BUGLER CONSTRUCTION, INC. PLEASANTON, CA $1,737,460.00 +0.0%
2 T.P.A. CONSTRUCTION, INC. ROSEVILLE, CA $1,925,165.70 +10.8%
3 FEC FUTURE CONTRACTORS AND ENGINEERS $3,096,634.00 +78.2%
4 GRANITE CONSTRUCTION COMPANY WATSONVILLE, CA $3,898,580.00 +124.4%
Want the full picture? Caltrans Tracker breaks down every line item, compares subcontractor pricing across bidders, and models cost history against Caltrans's own bid data — free preview, no card required.
Open 06-0U0004 in Caltrans Tracker →

CaltransTracker.com is an independent, privately owned data platform. It is not affiliated with, endorsed by, or operated by the California Department of Transportation (Caltrans) or the State of California. About · Privacy · Terms · Support this site