REPLACE BRIDGE
IN SAN LUIS OBISPO COUNTY IN MORRO BAY AT TORO CREEK BRIDGE
| Bid opened | 2021-02-17 |
|---|---|
| District | 05 |
| Engineer's estimate | $6,900,000.00 |
| Low bid | $5,759,455.40 -16.53% vs EE |
| Low bidder | SOUZA ENGINEERING CONTRACTING, INC. DBA SOUZA CONSTRUCTION |
| Number of bidders | 6 |
| Working days | 740 |
| Number of items | 131 |
| Source | Caltrans bid summary PDF ↗ |
| # | Bidder | City, State | Bid amount | vs Low |
|---|---|---|---|---|
| 1 | SOUZA ENGINEERING CONTRACTING, INC. DBA | SAN LUIS OBISPO, CA | $5,759,455.40 | +0.0% |
| 2 | CALPORTLAND CONSTRUCTION | SANTA MARIA, CA | $5,829,913.50 | +1.2% |
| 3 | PAPICH CONSTRUCTION COMPANY, INC. | ARROYO GRANDE, CA | $6,521,000.00 | +13.2% |
| 4 | BEADOR CONSTRUCTION COMPANY, INC. | $7,143,300.00 | +24.0% | |
| 5 | GOLDEN STATE BRIDGE, INC. | BENICIA, CA | $8,103,985.30 | +40.7% |
| 6 | GRANITE CONSTRUCTION COMPANY | WATSONVILLE, CA | $11,112,649.00 | +92.9% |