RECONSTRUCT CONCRETE LINED DITCH
IN SAN BRUNO FROM WHITMAN WAY UNDERCROSSING TO 0.1 MILE SOUTH OF SAN BRUNO AVENUE UNDERCROSSING
| Bid opened | 2020-11-18 |
|---|---|
| District | 04 |
| Engineer's estimate | $730,000.00 |
| Low bid | $478,908.00 -34.40% vs EE |
| Low bidder | AMERICA PACIFIC CONSTRUCTION |
| Number of bidders | 12 |
| Working days | 60 |
| Number of items | 31 |
| Source | Caltrans bid summary PDF ↗ |
| # | Bidder | City, State | Bid amount | vs Low |
|---|---|---|---|---|
| 1 | AMERICA PACIFIC CONSTRUCTION | EASTVALE, CA | $478,908.00 | +0.0% |
| 2 | GRANITE ROCK COMPANY | SAN JOSE, CA | $495,573.00 | +3.5% |
| 3 | EURO STYLE MANAGEMENT | NORTH HIGHLANDS, CA | $577,191.40 | +20.5% |
| 4 | JOSEPH J. ALBANESE, INC. | SANTA CLARA, CA | $635,965.00 | +32.8% |
| 5 | QUIMU CONTRACTING, INC. | DIXON, CA | $667,969.00 | +39.5% |
| 6 | HOSELEY CORPORATION | SAN FRANCISCO, CA | $676,323.16 | +41.2% |
| 7 | YERBA BUENA ENGINEERING & CONSTRUCTION, INC | SAN FRANCISCO, CA | $677,920.00 | +41.6% |
| 8 | VALENTINE CORPORATION | SAN RAFAEL, CA | $688,369.00 | +43.7% |
| 9 | CF CONTRACTING, INC. | SAN FRANCISCO, CA | $699,165.00 | +46.0% |
| 10 | GORDON N. BALL, INC. | ALAMO, CA | $737,708.00 | +54.0% |
| 11 | KEREX ENGINEERING INC NR NO DBE/DVBE SUBMITTAL | MARTINEZ, CA | $759,880.00 | +58.7% |
| 12 | GOLDEN BAY CONSTRUCTION, INC. | HAYWARD, CA | $887,467.00 | +85.3% |